camo556
Ultimate Member
- Aug 29, 2021
- 2,634
If we are correct about the permit numbers, we know how many applications are outstanding from 7/29 to 8/4: As of 8/4 MSP zoom call, there were 25k applications. As of today 16-17k have been approved. That means 8000-9000 apps remaining from between 7/29 and 8/4. It will take ~ 3-4 weeks to get through those at the current approval rate, putting 8/4 applicants around 75+ days from acceptance to approval. I think they will get through them a little faster because they will hire people.7/29 to 8/1 will be a big slow down. My trainer had qualification of all their July classes start on 7/31, and I expect each weekend after that date to have large number submission.